Screed calculator

This screed calculator turns your floor size and screed depth into the volume of screed, the cement bags and tonnes of sharp sand to mix it, or the cubic metres of liquid screed to order. Works in metres or feet.

Screed type
%

For an L-shaped room, split it into rectangles and add the results.

–m³ of mixed screed

  • –25 kg bags of cement
  • –sharp sand
  • –bulk bags of sand (850 kg)
  • –floor area

How to use the screed calculator

  1. Choose the screed type. Sand and cement is mixed on site. Liquid (anhydrite or flowing) screed is delivered and pumped, and ordered by volume.
  2. Measure the floor length and width wall to wall. Split L-shaped rooms into rectangles.
  3. Enter the screed depth, the finished thickness from the slab or insulation to the top of the screed.
  4. Pick the mix ratio. 1:4 cement to sharp sand is the usual floor screed.
  5. Keep a waste allowance of 10% for uneven slabs, spillage and the mix left in the mixer.

How much screed do I need? The formula

Screed volume (m³) = length (m) × width (m) × depth (mm) ÷ 1,000

A sand and cement mix shrinks as water fills the gaps between the grains, so you need more dry material than the wet volume. The calculator adds 30% (a factor of 1.3) to get the dry volume, then splits it by your mix ratio. Cement is taken at 1,440 kg/m³ and damp sharp sand at 1,600 kg/m³.

Worked example: a 5 × 4 m kitchen (20 m²) screeded 65 mm deep over insulation. 20 × 0.065 = 1.3 m³, or 1.43 m³ with 10% waste. The dry volume is 1.86 m³. At 1:4 that is about 535 kg of cement (22 bags of 25 kg) and 2.4 tonnes of sharp sand, so three 850 kg bulk bags.

Three screed sections: a bonded screed 25 to 40 mm on the slab, an unbonded screed at least 50 mm on a membrane, and a floating screed at least 65 mm on insulation
Bonded, unbonded and floating screeds need different minimum depths.

Cement and sand per square metre

1:4 sand and cement screed, per m², before waste
DepthWet volumeCementSharp sandTypical use
25 mm0.025 m³9.4 kg42 kgBonded screed
40 mm0.040 m³15 kg67 kgBonded screed
50 mm0.050 m³18.7 kg83 kgUnbonded on a membrane
65 mm0.065 m³24.3 kg108 kgFloating over insulation, underfloor heating
75 mm0.075 m³28.1 kg125 kgCommercial floating screed

Screed mix ratios

The British Standard for screeds, BS 8204, puts sand and cement floor screeds at 1:3 to 1:4.5 cement to sharp sand by volume. 1:4 is the everyday choice for domestic floors. Use clean sharp (concreting) sand, not soft building sand, which shrinks and cracks. Add only enough water for a semi-dry, "earth damp" mix that holds together when squeezed. Too much water weakens the screed and makes cracking more likely.

How thick should a screed be?

Sand and cement vs liquid screed

Traditional screed is cheap and can be laid in small areas by hand, but it is heavy work and slow to dry. Liquid screed (usually calcium sulphate or anhydrite) flows level, can be laid thinner over insulation and underfloor heating, and is pumped in by the supplier. It is ordered in cubic metres, which is the volume the calculator shows. Most suppliers have a minimum order of a few cubic metres.

Drying time

A common rule for sand and cement screed is about one millimetre per day for the first 40 mm, then about half a millimetre per day after that. That means a 65 mm screed can need two to three months before timber, vinyl or other moisture-sensitive floors go down. Test with a hygrometer before laying the floor finish. Liquid screeds can be force-dried with underfloor heating after about a week, following the maker's schedule.

Frequently asked questions

How much screed do I need?

Multiply the floor area by the depth in metres. A 20 m² floor at 65 mm needs 20 × 0.065 = 1.3 m³ of mixed screed, or about 1.43 m³ with 10% for waste.

How many bags of cement for a screed?

For a 1:4 sand and cement screed, allow roughly 24 kg of cement per m² at 65 mm deep, so about one 25 kg bag per square metre. A 20 m² floor at 65 mm with 10% waste needs about 22 bags of cement and 2.4 tonnes of sharp sand.

What is the mix ratio for floor screed?

A standard sand and cement floor screed is 1 part cement to 4 parts sharp sand by volume. 1:3 gives a stronger screed for heavy use, and 1:5 is used for thicker, lightly loaded floors.

How thick should a screed be?

A bonded screed can be 25 to 40 mm, an unbonded screed at least 50 mm, and a floating screed over insulation at least 65 mm in homes (75 mm in commercial buildings). Screeds over underfloor heating are typically 65 to 75 mm for sand and cement.

How long does screed take to dry?

A common rule for sand and cement screed is about 1 mm of drying per day for the first 40 mm, then about 0.5 mm per day after that. A 65 mm screed can take two to three months to dry fully before moisture-sensitive floors go down.